Earnings Insights · RIOT · Q3 FY2026
Riot Platforms Q3 2026 Earnings: Corsicana AI Lease Reshapes the Data Center Growth Profile
By AlgovestIQ ResearchPublished
Read Riot Platforms’s results announcement (Form 8-K, filed Nov 4, 2026)
Key earnings findings
Riot Platforms (RIOT) Q3 FY2026 · results discussed on the earnings call · Form 8-K filed
- Riot Platforms reported Q3 FY2026 revenue of $181.4M against the $160.8M analyst estimate, a 12.8% beat, and EPS of $0.01 against the -$0.34 analyst estimate.
- Riot continues to target development costs of $11M to $12M per MW for that Tier 3 project.
- RIOT closed at $15.37 on Nov 4, 2026, up 9.6% from $14.02 on Nov 3, 2026, the last close before the results were released.
Sources: Riot Platforms results announcement (SEC), the Q3 FY2026 earnings call, and AlgovestIQ reported-results and market data. All references
Did Riot Platforms beat earnings expectations?
- Revenue surprise across the last 8 reported quarters has ranged from -9.0% to 28.1%.
Reported figures against analyst estimates, compiled from AlgovestIQ data.
Riot Platforms reported Q3 2026 revenue of $181.4M, up 1% year over year, and GAAP net income of $4.0M, or $0.01 per diluted share. The headline financial results were largely flat as higher data center and engineering revenue offset a sharp decline in bitcoin mining revenue, but the quarter was defined by a much larger development: a 15-year, 910 MW powered-land lease at Corsicana with a Frontier AI Lab.
The Corsicana agreement substantially expands Riot’s contracted data center portfolio and shifts the company’s prospective cash flow mix away from bitcoin mining. The investment case now depends less on near-term mining economics and more on Riot’s ability to finance and deliver three large contracted developments on schedule and within budget.
Earnings Snapshot
| Metric | Reported | Change |
|---|---|---|
| Total revenue | $181.4M | Up 1% year over year |
| GAAP net income | $4.0M | Down from $104.5M |
| GAAP diluted EPS | $0.01 | Not provided for prior-year period |
| Adjusted EBITDA | $191.3M | Down from $197.2M |
| Data Center revenue | $18.4M | First full quarter of stabilized AMD capacity |
| Bitcoin Mining revenue | $116.0M | Down from $160.8M |
| Engineering revenue | $47.0M | Up from $19.1M |
| Bitcoin produced | 1,637 | Up from 1,406 |
| Cost to mine bitcoin, excluding depreciation | $39,265 | Down from $46,324 |
| Cash and bitcoin | $950.2M | Includes $748.2M of cash and 2,418 bitcoin |
| Bitcoin sold year to date | 20,264 | Approximately $1.5B of proceeds |
The Bigger Story
Riot signed a 15-year triple-net powered-land lease for the full 910 MW Corsicana campus with a Frontier AI Lab. Management estimates the agreement represents approximately $28B of total contract value over the initial term, approximately $1.8B of average annual rent including escalators, and roughly $1.8B of annual net operating income under its triple-net structure.
The transaction changes Riot’s planned role at Corsicana. Rather than building and operating a conventional Tier 3 data center, Riot will provide land, power infrastructure and powered pads. The tenant will procure, own and operate its modular compute deployment, pay utility costs as a pass-through, and bear most operating expenses.
That structure materially lowers Riot’s expected capital commitment and operating exposure. Riot estimates total Corsicana project costs of approximately $5.5B, or $6M per IT MW, with roughly $2M per MW for Riot’s site and electrical work and $4M per MW for tenant reimbursements. Those reimbursements are due in phases after a delivered phase has begun generating rent.
Management said rent will be paid on the full 910 MW regardless of the tenant’s utilization. That improves contractual visibility, but the project still requires delivery of substantial power infrastructure and a large financing program before the projected rent stream begins.
Riot said it has now leased 1,151 MW across its AMD deployment, the previously announced Frontier AI Lab lease at Rockdale, and Corsicana. The company’s press release places total long-term contracted data center revenue at approximately $38B. Management’s prepared remarks referred to approximately $3.8B at one point, a figure that conflicts with the $38B figure used elsewhere for the three-lease portfolio.
Revenue and Operating Performance
Revenue increased just 1% to $181.4M because the growing data center and engineering businesses offset weaker bitcoin mining revenue.
Bitcoin Mining revenue fell 28% to $116.0M from $160.8M a year earlier. Riot produced 1,637 bitcoin, up 16% from 1,406, but the average production value per bitcoin declined to $70,855 from $114,361 in the prior-year quarter. The lower realized bitcoin value more than offset higher production.
Mining output benefited from a deployed hash rate of 44.9 exahash per second at quarter end, although average operating hash rate was 36.2 exahash during the quarter because Riot curtailed operations during periods when power-market programs were more attractive.
Data Center revenue was $18.4M, reflecting the first full quarter of the stabilized 25 MW delivered to AMD. The segment included $7.7M of base rent, $0.5M of variable lease revenue and $10.2M of tenant fit-out reimbursement revenue.
The distinction is important for revenue quality. Base rent and variable lease revenue represented recurring operating revenue, while tenant fit-out reimbursement revenue is tied to the construction cycle and will fluctuate with development activity. Management said the 25 MW of operating AMD capacity equates to roughly $31M of annualized base rent, with another 10 MW expected to be delivered during November.
Engineering revenue more than doubled to $47.0M from $19.1M, driven by third-party data center demand for custom electrical equipment. However, management said segment gross margin was 15%, reflecting a large, lower-margin cable procurement order at E4A Solutions. Engineering backlog was $142M, with more than 90% related to data center work.
Profitability and Margins
GAAP net income fell to $4.0M from $104.5M in the prior-year period, despite revenue growth. The quarter included $123.9M of depreciation and amortization, $21.4M of stock-based compensation expense, a $26.3M derivative fair-value change, and an $18.5M impairment of property and equipment.
Adjusted EBITDA was $191.3M, down modestly from $197.2M a year earlier. The measure excludes several non-cash and non-recurring items, including derivative fair-value changes, stock-based compensation and impairment charges. It should therefore be viewed alongside the much lower GAAP net income.
Mining economics improved on a cash-cost basis. Riot’s cost to mine bitcoin excluding depreciation declined to $39,265 from $46,324 a year earlier, supported by lower power costs and higher production. The company received $24.7M of power curtailment credits during the quarter, equivalent to $15,067 per bitcoin mined.
However, including depreciation, Riot’s cost to mine was $78,805 per bitcoin, above the quarter’s $70,855 production value per bitcoin. That illustrates why mining profitability remains sensitive to bitcoin prices, network conditions and the level of curtailment credits available.
Demand, Customers and Pricing
The newly signed Corsicana lease indicates that demand for large, powered AI infrastructure remains strong, particularly for capacity with already approved interconnections and existing on-site power infrastructure.
Management said the Corsicana tenant wanted control of the entire site rather than a smaller allocation. The company also said the tenant’s preference for a modular deployment allowed Corsicana to support 910 MW of critical IT capacity, compared with Riot’s earlier expectation of 756 MW under a more conventional Tier 3 design.
At Rockdale, AMD retains options for up to an additional 150 MW. Management said Riot has roughly 200 MW to 250 MW of remaining leasable capacity at Rockdale and expects that capacity could ultimately be taken by AMD, the Frontier AI Lab tenant, or other interested customers.
The growing concentration of Riot’s data center business among a small number of large tenants improves the visibility of contracted rent but also makes delivery, tenant credit quality and lease execution more consequential.
What is Riot Platforms’ outlook for the remainder of 2026 and 2027?
Riot did not provide formal financial guidance for revenue, EPS or adjusted EBITDA. Management instead focused on development milestones, financing and the expected ramp of contracted lease revenue.
The company expects the AMD deployment at Rockdale to reach 50 MW in May 2027. The next 10 MW is expected to be delivered in November 2026.
For the 191 MW Frontier AI Lab project at Rockdale, management expects the first 96 MW to be ready for service in December 2027 and the remaining 95 MW in June 2028. Riot continues to target development costs of $11M to $12M per MW for that Tier 3 project. Management said approximately 70% of the project budget is expected to be covered by guaranteed maximum-price contracts, with remaining exposure related primarily to owner-furnished equipment and other non-GMP scopes.
Corsicana is expected to be delivered in three phases: 400 MW in September 2027, 200 MW in January 2028 and 310 MW in July 2028. Rent on each phase is expected to begin no later than 60 days after delivery of the powered pads.
Management expects lease revenue to rise from approximately $23M in 2026 to approximately $250M in 2027, $1.8B in 2028 and $2.3B in 2029, when all currently contracted capacity is expected to be in service. These figures are management projections and include lease accounting considerations: management noted that tenant reimbursement amortization will reduce reported lease revenue over the contract term relative to the cited Corsicana rent and NOI figures.
Balance Sheet, Cash Flow and Capital
Riot ended the quarter with $950.2M in cash and bitcoin, including $748.2M of cash, of which $79.2M was restricted, and 2,418 bitcoin valued at approximately $202.0M at September 30.
The company sold 20,264 bitcoin for approximately $1.5B during the first nine months of 2026, primarily to fund data center development. It also repaid and terminated its $200M Coinbase credit facility, releasing pledged bitcoin collateral.
The financing requirement remains substantial. Riot estimates that Corsicana and Rockdale will require approximately $7.6B to $7.8B of total project capital, excluding additional AMD CapEx expected to be financed through a separate AMD bank facility. Management expects approximately $6.1B to $7.0B to be funded by non-recourse project debt, leaving an estimated Riot cash-equity requirement of $800M to $1.5B through mid-2028.
For Corsicana, management’s base case is project debt at an illustrative 80% to 90% loan-to-cost ratio. If comparable financing is not available, the tenant would initially fund reimbursements and recover them through rent credits over the remaining lease term. Management said those rent credits would carry an implied 12% interest rate.
Riot does not currently anticipate issuing equity for its announced projects. That expectation depends on project financings, expected rent receipts, existing liquidity and other potential non-dilutive funding sources remaining available on acceptable terms.
What Investors Should Watch
1. Project financing execution
Riot’s development plan depends on several large non-recourse financing transactions. The timing, leverage levels, interest costs and lender requirements for Rockdale and Corsicana will determine how much internal cash Riot must commit.
2. Delivery against the 2027-2028 schedule
The first major Corsicana phase is due in September 2027, followed by Rockdale’s initial Frontier AI Lab phase in December 2027. Timely delivery is essential because rent commencement and reimbursement timing are tied to completed phases.
3. Capital-cost discipline at Rockdale
Riot continues to target $11M to $12M per MW for the Tier 3 Rockdale build. Progress in placing more work under guaranteed maximum-price contracts will be an important measure of protection against cost inflation and construction overruns.
4. Conversion from mining to data center cash flow
Riot expects to continue selling substantially all bitcoin it mines while development spending remains elevated. Investors should monitor mining cash costs, bitcoin prices and curtailment credits because mining remains the near-term source of operating cash flow.
5. The pace and quality of lease revenue recognition
The company’s cited contract values, rents and NOI are long-term economic estimates. Reported lease revenue will ramp according to delivered capacity and will be affected by accounting for tenant reimbursements.
AlgovestIQ Takeaway
Riot’s Q3 financial results were modest: revenue grew 1%, GAAP earnings fell sharply from the prior-year quarter, and mining revenue remained highly exposed to bitcoin pricing. The operating improvement in mining cost per bitcoin was meaningful, but depreciation left the all-in cost to mine bitcoin above the quarter’s average production value.
The Corsicana lease is the more consequential development. It expands Riot’s contracted AI infrastructure portfolio at a lower stated capital intensity than a traditional Tier 3 build and shifts significant operating, technology and power-price risk to the tenant. If delivered as structured, the deal could materially reduce Riot’s dependence on bitcoin mining economics.
The central investment question is now execution rather than leasing demand. Riot has signed contracts that management says could generate approximately $2.3B of annual lease revenue and $2.2B of annual NOI at full deployment, but most of that cash flow remains dependent on construction, tenant reimbursement mechanics and large-scale project financing through 2028.
Evidence that would strengthen the thesis includes completed project financings on acceptable terms, continued adherence to Rockdale’s cost budget, and on-time delivery of AMD, Rockdale and Corsicana capacity. The thesis would weaken if debt markets require more Riot equity than expected, construction costs rise outside contracted protections, or project schedules slip and delay rent commencement.
How did RIOT stock react?
RIOT closed at $15.37 on Nov 4, 2026, up 9.6% from $14.02 on Nov 3, 2026, the last close before the results were released.
| Session | Close | Change |
|---|---|---|
| Nov 3, 2026 (before release) | $14.02 | — |
| Nov 4, 2026 | $15.37 | +9.6% |
| Nov 5, 2026 | $14.76 | +5.3% |
Closing prices from AlgovestIQ market data. A move around a report also reflects the wider market.
More from this earnings season
- HUTHut 8 Q3 2026 Earnings: AI Data Center Pipeline Expands, but Revenue Still Awaits DeliveryNov 4, 2026
- HOODRobinhood Q3 2026 Earnings: Record Revenue as Prediction Markets Offset Crypto WeaknessOct 27, 2026
- SCHWCharles Schwab Q3 2026 Earnings: Record Asset Flows and Lending Drive Margin ExpansionOct 15, 2026
- MSMorgan Stanley Q3 2026 Earnings: Equities and Wealth Flows Offset a Weaker Investment Management QuarterOct 14, 2026
- GSGoldman Sachs Q3 2026 Earnings: Equities Financing and Asset Fees Offset a Slower Markets QuarterOct 13, 2026
References
- Management commentary, analyst questions and outlook discussed on the call. Source: Riot Platforms Q3 FY2026 earnings call transcript, as of Nov 4, 2026.
- Reported results, segment figures and guidance from the company's results announcement. Source: Riot Platforms Form 8-K, Item 2.02 (SEC EDGAR), as of Nov 4, 2026.
- Reported revenue and EPS against analyst estimates, and the reported quarterly series. Source: AlgovestIQ reported-results data, as of Nov 4, 2026.
AI-generated analysis based on company-reported earnings data and earnings-call materials. Not investment advice.